Projects

Installation, Testing, commissioning& Energization Substations

400/132/11 KV GIS equipment AL-Ameen SS                      2002 – 2004

132/33KV GIS equipment AL-Washash SS                           2005

132/33/11KV GIS South Sulamanya SS                                   2005

132/33/11 KV GIS Um Qasar SS                                               2006

400/132/33/11 KV GIS equipment AL-Rasheed SS              2006 – 2007

132/33 KV GIS Al Baker SS                                                     2010

72/20 KV GIS equipment Damasus gate (Syria) SS           2011

132/11 KV GIS Al Rusafa SS                                                     2012

132/33 KV GIS Nasiriyah SS                                                   2013

132/33 KV GIS New Bab Al Zubair SS                                   2013

132/33 KV GIS Al Acadimiya SS                                            2014

400/132/11 KV GIS South Al-Nasiriyah SS Diameter 1        2020

132/33 KV GIS Al-Matar SS                                                   2020

132/33 KV GIS Al-Mahad SS                                                 2020

132/33 KV Qalat Salih GIS SS                                                2020

132/33 KV GIS Al-Massab Al-aam SS                                  2021

400/132/11 KV GIS South Al-Nasiriyah SS Diameter 2       2022

132/33 KV GIS Qurna west 2 oil filed Well-paid 4              2023

132/33 KV GIS Qurna west 2 oil filed Well-paid 9              2023

33/11/0.4 KV GIS ss Al-Zubair oil Filed                                 2024

33/11/0.4 KV GIS ss  Al-Rafidiyah oil Filed                           2024

Rehabilitation of Substations equipment

Project SS 174 (Gammas, Altahrer, Aleskandriya, Baled, Sumria, Dura, New Mishraq)                      2005 – 2007
Project NT 15 (New Wazeria, Hilla North,Muqdadya)                                                                            2009 – 2010
Project NT 18 (Abo flus, Alhussainiya, New Hammam)                                                                         2009 – 2011
Project NT 16 (Al Tabadel Al Tijiry, Basrah West,Khanqeen)                                                                2010 – 2011
Project NT 38 (Amara north, Hilla East, Nijaf West)                                                                             2010 – 2011
Project NT 24 (Kirkok East, Al Tameem,Hilla West )                                                                             2010 – 2011
Project NT 26(New Fao, AliZfraniya, Abodisheer, Mosul East, Kerbala East)                                     2010 – 2012
Project NT 83 (Baladrose, Baweza, Ramady South, Tikrit East)                                                          2011 – 2012
Project STX (Substation North Refineries)                                                                                            2013
Qurna West 2 – 132/33 KV SS                                                                                                                2013

Checking and adjusting the relay settings of BNGL (Manpower)                                                      2025

3.3/0.4 (AlDawra Oil Refinery) Manpower                                                                                                  2025 

(Zuber one) Manpower                                                                                                                           2025

Installation 33kV, 11kV,0.4 (Baiji Oil Refinery)                                                                                        2025

Installation 0.4/6.6 transformer ( Artawi Al-Rumaila Al-Shamaliyah)                                               2026

Installation 33kV, 11kV,6.6/0.4 (IGC)                                                                                                       2026

Installation 132/33KV Transformer (MOE Daquq Station)                                                                  2026

Installation 132/33KV Transformer (Artawi Al-Rumaila Al-Shamaliyah )                                          2026

Maintenance of the Power transformer

Maintenance of power transformers for generators No, 2,5,9,11 –Mullabed allah Power Generation Plant          2012 – 2014

Maintenance of power transformers for generators (Aqra Water Project)                                                              2019
Assembling 33/11KV Power transformer at Grraf oil field                                                                                            2022

Maintenance of Water plant generation station

Water plant generation station /Mosul Dam                                                                                                                 2007 – 2008

High voltage test

Project SS 174 (Dura, New Mishraq GIS SS)                                         2008

Project NT 15 (New Wazirea GIS SS)                                                    2010

Project NT 18 (New Hummam GIS SS)                                                 2010

Project NT 16 (Basrah West GIS SS)                                                     2011

Project NT 26 (New Fao GIS SS)                                                           2011

Project NT 1(Rusafa GIS SS)                                                                  2012

Project NT  117 (Al Acadimiya , New Bab Al Zubair  GIS)                    2014

Damascus (Gate 8) 72 KV GIS SS /Syria                                             2011

Al-Masab AlAlaam 132/33KV GIS                                                        2020

South Nasiriyah 400/132KV                                                                2022

Rumaila North Oil filed 132KV cables                                                 2023 

BNJL H.V VLF Test                                                                                2026